PROGRESS PROJECT
PT. UTOMODECK METAL WORK

PERUSAHAAN : PT. ECCO TANNERY INDONESIA | PROYEK : ECCO | NO. KONTRAK : PO 4600005520

KONTRAK TERPASANG PROGRESS
MATERIAL Quantity M` M2 Quantity M` M2 Quantity M` M2
UTOMOZIP 0 0 6939 2434 17092.55 7178.871 0,00% 0,00% 103,46%
FLASHING 0 568.28 0 0 0,00% 0,00% 0,00%
NOK STANDART 0 493.56 0 51 249.9 149.94 0,00% 50,63% 0,00%
TALANG 0 819.56 0 26 150.8 0 0,00% 18,40% 0,00%
PIPA DOWNSPOUT 0 800 0 0 0,00% 0,00% 0,00%
SHOCK PIPA DOWNSPOUT 0 65 0 0 0,00% 0,00% 0,00%
DINDING JACKROOF 0 52 0 0 0,00% 0,00% 0,00%
JACKROOF ALUMINIUM 0 753 0 0 0,00% 0,00% 0,00%
FIBER UTOMOLITE 0 780 0 0 0,00% 0,00% 0,00%

No. Tanggal Material Quantity (Pcs/Lembar/Unit) Panjang (cm) Lebar (cm) M' M2 Mandor Keterangan
1 2019-03-09 02:28:58 talang 26 580 0 150.8 0 agung Gedung A
2 2019-03-09 02:25:52 utomozip 338 900 42 3042 1277.64 agung Gedung A
3 2019-03-09 02:24:52 utomozip 261 1265 42 3301.65 1386.693 agung Gedung A
4 2019-03-05 08:02:22 utomozip 162 1265 42 2049.3 860.706 agung gedung A
5 2019-02-18 08:42:55 utomozip 145 520 42 754 316.68 agung Monitor D
6 2019-02-16 08:02:47 utomozip 217 520 42 1128.4 473.928 agung Monitor D
7 2019-02-14 06:30:30 utomozip 67 520 42 348.4 146.328 agung Monitor D
8 2019-02-12 02:40:21 utomozip 46 520 42 239.2 100.464 agung Monitor D
9 2019-02-09 03:15:39 utomozip 63 520 42 327.6 137.592 agung Monitor C
10 2019-02-09 03:10:48 nok 7 490 60 34.3 20.58 agung
11 2019-02-07 15:43:36 nok 17 490 60 83.3 49.98 agung
12 2019-02-07 05:06:06 nok 27 490 60 132.3 79.38 agung
13 2019-02-07 02:05:52 utomozip 163 520 42 847.6 355.992 agung Monitor C
14 2019-02-02 01:15:07 utomozip 42 520 42 218.4 91.728 agung Monitor B
15 2019-01-31 13:46:50 utomozip 80 520 42 416 174.72 agung Monitor B
16 2019-01-30 06:16:04 utomozip 43 520 42 223.6 93.912 agung
17 2019-01-30 05:50:54 utomozip 118 520 42 613.6 257.712 agung
18 2019-01-29 04:53:38 utomozip 383 520 42 1991.6 836.472 agung Gedung A
19 2019-01-29 04:50:50 utomozip 306 520 42 1591.2 668.304 agung Gedung A

CREATED BY TOMCAT46